Our
Processing Plant
A Work in Progress
Construction of our plant officialy begun on 01 January 2024. Whatch this space to keep up to date with the progress.
01 January 2024
.
Building Began
It is a long established fact that a reader will be distracted by the readable content.
1 June 2024
.
June Update
- Completion of the access road to the site up to the subbase level. - Platform fills to all major production areas are finished. - Construction of the lairage buildings is ongoing. - Foundation excavations for the slaughter floor, deboning hall, and dispatch areas are completed. - Foundation plinths for the slaughter floor have been constructed. - The first steel columns have been erected on the slaughter floor. - Sleeving to house services is currently being installed.